Case study: restructuring supplier payment terms to free up cash flow for MakersBolt

The problem

Cash flow was the client’s main worry. A lot of capital was sitting in inventory at the supplier’s warehouse and at GWD.

We’d already negotiated 90-day payment terms from the B/L date. That works fine for fresh stock. It works badly for older inventory that can sit at GWD for a long time, because the clock doesn’t start until the B/L date. The supplier waits, and the client carries stock it hasn’t paid for or sold.

The old setup

Supplier warehouse → GWD → U.S.

100% of payment was due 90 days after the B/L date. One payment, one deadline, no matter how long the stock had already been sitting.

What we negotiated

We took the stock being transferred to GWD and asked the supplier for a different structure:

  • 30% due the day the inventory leaves the supplier’s warehouse for GWD

  • 70% due on the B/L date, when the GWD shipment departs for the U.S.

Same route as before. Different timing on the money.

Why the supplier agreed

The supplier gets 30% as soon as the older inventory starts moving out of their warehouse. That improves their working capital and clears space on their floor. Under the old terms, they’d have waited months for any of it.

For MakersBolt, the other side of that trade is that the full inventory value isn’t paid while stock sits idle at GWD. The bulk of the cash, 70%, stays put until the shipment is actually headed to the U.S.

The result

The client avoids a large upfront payment, and the supplier gets paid earlier against the older stock. Both sides came out ahead.

I think the useful part here is that the 90-day terms weren’t wrong; they just didn’t fit one slice of the inventory. Looking at where the stock actually sits and for how long is what exposed the gap.